CLIENT: Changi Airport Group
PROJECT COMMENCE DATE: 01/07/2019
PROJECT COMPLETION DATE: Mar 2023
DESCRIPTION: Construction of Rigid Pavements for 4 nos of New Parking Bays, Semi-Rigid Pavement for airside roadway, Reconfiguration of Airside Fencing, RC pile, Hot Mix Asphalt Concrete (HMAC), Grated Drain, Cable Ducts, Hydrant Pipe and Potable Water Pipe System with associated M&E works including High Mast, INS Sign, CCTV, ADGS and etc.
DESCRIPTION: Construction of 330 meter of backoff drain below the parking apron and Taxiway.
DESCRIPTION:Construction of 13,000 meter square of Taxiways which consists of 6 layers of subgrade compaction and 5 layers of flexible pavement with required density.