Reconstruction of Taxilane L4 Singapore Changi Airport


CLIENT: Changi Airport Group
PROJECT COMMENCE DATE: 25/09/2019
PROJECT COMPLETION DATE: 17/10/2019


DESCRIPTION: To excavate the existing taxilane L4 and construct a new flexible pavement.

CHALLENGE: A shortest time frame ever. Take only 16 days to completion.